Failed ramps, cost overruns, years of delays: School construction projects infuriate NYC parents

A group of students walk through construction.
Students leave NEST+m Tuesday, October 21, 2025, after classes are dismissed and use the ramp that's still under construction. An adult ordered students to stop using the ramp minutes after this photo. (Ananya Chetia / Chalkbeat)

Sign up for Chalkbeat New York’s free daily newsletter to get essential news about NYC’s public schools delivered to your inbox.

Construction began at a Brooklyn elementary school four years ago to make its building more accessible for students with disabilities.

A new entrance ramp was among the projects at Red Hook’s P.S. 15, where more than 62% of the students have disabilities.

But the seemingly straightforward construction project has not yet been completed, said Katina Rogers, a Brooklyn mom and president of the local parent education council advising on District 15’s needs.

Parents were frustrated that the city paid $11 million for the project, which included window replacements and exterior work, despite the work remaining unfinished — and building conditions were worse than when the project started, they said.

“For that to be happening in an underserved community, it’s really a problem,” Rogers said.

The ramp project at P.S. 15 is just one example of lengthy delays, shoddy work, and cost overruns for projects overseen by the School Construction Authority, according to more than a dozen interviews with parents, a former high school student, and elected officials. The problems at the agency have sparked widespread concerns among parents and educators. Over the past two years, at least seven elected parent boards have called for stricter oversight or asked the City Council to create a task force to reform the agency.

Many parent leaders worry the agency is buckling under the weight of its responsibilities: Beyond building improvement and renovation projects, the city is projecting the School Construction Authority will oversee an estimated $18 billion effort to add seats to help the city comply with the state’s class size reduction law.

Another ramp at a Manhattan school had to be fixed twice in less than two years. And a Queens school has been waiting for more than a year for a building inspection so it can install air conditioning and fix auditorium chairs.

Manhattan’s District 3 Community Education Council, covering the Upper West Side and part of Harlem, said in a resolution last year that School Construction Authority delays have left many of its schools under scaffolding for years, “negatively impacting student learning, school operations, and community wellbeing.”

Because school leaders don’t have authority over these projects, it leaves “principals and families uninformed and without recourse.”

The Community Education Councils, volunteer boards whose duties include recommending improvements to school buildings, say vacancies at the agency have hobbled its operations.

The mayor is responsible for appointing all three trustees to the agency, but Mayor Eric Adams didn’t appoint the final member for nearly two years. The agency announced Elizabeth Bergin, former vice president of capital plan management at the SCA, as its third appointee in April. The agency has more than 90 vacancies, representing less than 9% of its total headcount, officials said. More than half of the vacancies are roles that require specific technical knowledge, including certain licenses. Officials said the agency is actively recruiting to fill the open roles.

Mayor-elect Zohran Mamdani has pledged to fill empty positions at the agency, saying the vacancies make it difficult to address overcrowding in schools.

Agency officials said they look for ways to save time and offset unplanned delays of their capital improvement projects, whether the work is for exterior or interior upgrades and other necessary capital repairs. They also noted that construction must take place after school hours, typically from 4 p.m. to midnight, for safety reasons, and that they frequently engage with principals before — and during — the construction process.

“The SCA works diligently to complete this work as efficiently and unobtrusively as possible, while maintaining the highest standards of safety for students and staff,” SCA spokesperson Kevin Ortiz said in an email. “In instances where [capital] projects experience delays, they are often due to the discovery of additional repair needs or unforeseen field conditions that impact the project’s scope and timeline.”

SCA oversees a huge portfolio with thousands of contractors

The School Construction Authority was created by the state in 1988, replacing the Board of Education’s Division of School Facilities, as an independent authority responsible for construction projects at public schools. There still is a Division of School Facilities that is separate from the SCA and oversees routine maintenance and smaller repair projects. (Charter schools do not rely on SCA to complete construction projects.)

The SCA tracks the progress of its capital improvement projects, which could include building a new single-occupancy bathroom, upgrading a swimming pool, or constructing a ramp. In 2024, more than half, or 57%, were not completed on time, according to public data.

In contracting projects, SCA chooses the lowest qualified bidder (and the contractor can find a subcontractor) that will finish the construction project. The SCA currently has roughly 2,100 contractors, according to NYC OpenData.

Depending on the size and type of project at a school, the School Construction Authority conducts routine inspections. That process has resulted in lengthy delays and complaints from school communities.

Queens resident Shirley Lee has fond memories of attending P.S. 21 almost 30 years ago. Today, the school’s auditorium bakes in the heat and has jagged metal sticking out of some of the chairs.

Lee, vice president of the Community Education Council in District 25, said funding was approved more than a year ago to install air conditioning and fix the chairs, but the School Construction Authority has yet to inspect the place.

Roughly 10% of the over 100 auditorium chairs are damaged, with cautionary tape blocking them off, Queens mom Christine Huang estimated.

“We were never able to get a straight answer for why nothing was being done,” Huang said about the SCA. The delays in school construction projects angered her so much, she decided to join the district’s education council and push for changes.

After this story initially published, SCA officials said no inspection was needed because the auditorium project was not moving forward. The approved funding was insufficient, so the school used it instead to pay for technology equipment.

“The auditorium project was not set to go forward because it was underfunded,” said Ortiz, from the School Construction Authority. “Funds were transferred to a technology project as agreed upon by the principal and Council Member.”

Noah Harlan, a member of Manhattan’s Community Education Council in District 1, said his daughter and other students have been unable to use parts of the playground at NEST+m, a school on the Lower East Side, for nearly two years because of multiple construction projects, including an elevator, to improve accessibility.

The construction authority has renovated the school’s ramp, which lines the building’s entrance, multiple times in less than two years, Harlan said. But blocking off the ramp disrupts dismissal for roughly 1,600 K-12 students. He noted after-school pick-up can get chaotic.

“When the ramps are closed, [the students] are all forced into the same areas, and it’s not ideal to have 12th graders and kindergarten students all transiting the same space,” Harlan said.

Ortiz noted that the school’s accessibility project has received “overwhelming support” from the NEST+m community.

Parents demand more transparency and oversight

Parents and education council resolutions have proposed the School Construction Authority create a public dashboard to track progress and delays for projects. There are currently over 6,000 planned or ongoing projects, according to the agency’s spokesperson.

Council member Vickie Paladino said her colleagues on the City Council haven’t done enough to address issues with the construction authority. Her office has earmarked roughly $15 million since 2022 for school projects, and she wants a better accounting of the spending.

Rita Joseph, who chairs the Council’s education committee, told Chalkbeat she plans to convene a hearing about the agency next year.

“We will continue to push to make sure that there’s transparency, accountability, and fiscal responsibility as well,” she said.

Rogers’ Brooklyn parent council suggested the agency participate in community listening sessions. Another parent council in Manhattan believes the construction authority needs to appoint a coordination team to improve communication between schools and families.

The agency said it’s looking into engaging with school communities early in a project to develop “realistic and flexible” plans.

Correction: This story initially said the P.S. 15 ramp had to be ripped out and replaced. It hasn’t been ripped out, but is getting a mid-landing, which is expected to start construction in summer 2026. And the ramp at Nest+m had to be replaced twice, not four times.

Ananya Chetia is a reporting intern with Chalkbeat NY. Contact the team at ny.tips@chalkbeat.org.

The Latest

In its first meeting in five months, the nine-member MSCS oversight board said the district needs strong leadership and teacher retention to see “dramatic gains” in achievement.

The school closure plan would merge campuses, shift programs, and affect families navigating the enrollment window.

Register to join our virtual event on Dec. 8 to hear Hanford make the case for a new approach to teaching.

Merci Ames’s youthful ambivalence about school has shaped how she approaches her work as a high school science teacher.

The nationwide blue wave has changed the political makeup of the Indiana General Assembly.

If backed by members and the school board, the historic agreement would increase pay and strengthen protections against harassment and overly punitive discipline for school leaders.